South San Francisco, CA March 7, 2016 from Caltrans
Caltrans will begin Phase 3 of the 101/Broadway Interchange Project. Beginning on the weekend of March 4-6, 2016 between the hours of 9:00 PM and 5:00 AM, the intersection of Broadway and Rollins Road will close to switch traffic from the existing Broadway Overcrossing to the new Broadway Overcrossing. The above map shows the traffic configeration and is expected to ease traffic congestion compared to the current configuration. The existing bridge will be demolished shortly after traffic has been switched over to the new structure.
The demolition of the bridge must be done during night-time hours to allow for full-highway closures of U.S. Highway 101 on two consecutive weekends. Route 101 southbound will close Saturday and Sunday mornings between 1:00 AM and 7:00 AM, March 12–13. Route 101 northbound will close Saturday and Sunday mornings between 12:00 AM and 6:00 AM, March 19–20. Traffic will be detoured onto local streets (detours will be clearly marked). Various lane and ramp closures will also be necessary for this work. Changeable message signs will be posted to notify motorists of the upcoming closure.
This traffic configuration will be in effect for approximately 10 months. Motorists should expect significant delays and are encouraged to consider alternate routes during this construction.
NOTE: The Bridge will be demolished with heavy equipment. Local residents and businesses may experience increased noise levels. This construction work is weather dependent.
For additional details, please contact Gidget Navarro, Caltrans Public Information O cer, at (510) 286-5574, or please refer to the project website CLICK HERE