Upcoming Caltrain Construction

February 7th, 2023 – South San Francisco, CA

Media Release

Caltrain Construction Weekly Notice

February 6 to 10

 Upcoming Caltrain Weekend Service Shutdowns

To finish critical Electrification construction and testing in time to begin passenger service in 2024, Caltrain will be suspending rail service in select areas on weekends throughout the year starting February 11, 2023. The first shutdowns will be between San Francisco and Millbrae for four weekends in February and March. Riders should avoid Caltrain on these weekends and seek alternative transportation if they are planning to travel. Bus bridge service will be available to Caltrain-dependent riders, but passengers should expect delays and longer travel times. Visit www.caltrain.com/status for the latest information about weekend impacts.

Weekday service will not be impacted. For more information about Caltrain’s weekday schedule, visit www.caltrain.com/schedules.

Caltrain Electrification

Caltrain Electrification is a key component of the Caltrain Modernization program which will electrify the Caltrain Corridor from San Francisco’s 4th and King Caltrain Station to approximately the Tamien Caltrain Station.

The primary purpose of Caltrain Electrification is to improve Caltrain system performance, reduce long-term environmental impact by reducing noise, improving regional air quality and reducing greenhouse gas emissions. An electrified Caltrain system would better address Peninsula commuters’ vision of increased service and improved travel times in an environmentally friendly and reliable way. This also is expected to help accommodate increase system ridership through improved system operations.

San Francisco

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, install wires and poles, install Overhead Contact System bridge attachments at the I-280 bridge. Caltrain will be working during the night to perform signal work, install cantilevers, assemblies, and stringing wire. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the 22nd Street station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Brisbane

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, and ground installation and testing of Overhead Contact Systems. Caltrain will be working during the night to perform signal work, install cantilevers, assemblies, and stringing wire. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Bayshore station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

South San Francisco

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit and install wires. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, install conduit, and install wires and poles. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

San Bruno

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit and install wires. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, install conduit, and install wires and poles. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Millbrae

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit and install wires and poles. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, install conduit, and install wires and poles. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Burlingame

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Burlingame and Broadway stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

San Mateo

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the San Mateo, Hayward Park and Hillsdale stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Belmont

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Belmont Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

San Carlos

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the San Carlos Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Redwood City

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Redwood City Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Unincorporated San Mateo County

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

Atherton

February 6 to February 10, Caltrain will be working during the day to perform signal work and install conduit. Caltrain will be working during the night to perform signal work, install crossing arms and arm foundations, and install conduit. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

Menlo Park

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, perform tree pruning, and test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to perform signal work and test wires and Overhead Contact System infrastructure. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Menlo Park Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Palo Alto

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, perform tree pruning, and test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to perform signal work and test wires and Overhead Contact System infrastructure. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Palo Alto and California stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.

Mountain View

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, perform tree pruning, and test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to perform signal work and test wires and Overhead Contact System infrastructure. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Mountain View and San Antonio stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Sunnyvale

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, perform tree pruning, and test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to perform signal work and test wires and Overhead Contact System infrastructure. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Sunnyvale and Lawrence stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

Santa Clara

February 6 to February 10, Caltrain will be working during the day to perform signal work, install conduit, perform tree pruning, and test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to perform signal work and test wires and Overhead Contact System infrastructure. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Santa Clara station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

San Jose

February 6 to February 10, Caltrain will be working during the day to perform signal work and to test wires and Overhead Contact System infrastructure. Caltrain will be working during the night to demobilize Overhead Contact System infrastructure at the Guadalupe River Bridge in San Jose in preparation for upcoming bridge replacement work. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

During work hours at the Diridon, Tamien and College Park stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

For more information, please call the dedicated outreach line at 650.508.6499; visit the website at caltrain.com/projects/electrification

or email [email protected]

 

Maintenance and Other Projects

Caltrain will perform routine maintenance at several locations next week. To avoid disruptions to service, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. For more information about this type of work, click here, or call 650.660.4287.

 

San Francisco to San Jose

Crews will pressure wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.

 

Crews will weld and grind rail at various locations between the San Francisco and Tamien stations. The welding crew uses air compressors, gas-powered generators, small power tools, electric-arc welders and propane heaters. Neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

Construction crews may be making repairs and replacing parts of a fence near the tracks and Jerrold Ave in San Francisco. Crews may also be installing fencing along Caltrain tracks near Paul Ave. and Gould St.

 

Brisbane to San Bruno

Crews will resurface rail between the Brisbane and San Bruno stations. Caltrain uses several different on-track, self-propelled machines to replace resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

San Bruno to Burlingame

Crews will resurface rail between the San Bruno and Burlingame stations. Caltrain uses several different on-track, self-propelled machines to resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

Burlingame to Mountain View

Crews will resurface rail between the San Bruno and Burlingame stations. Caltrain uses several different on-track, self-propelled machines to resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

Construction crews may be removing and replacing fencing near the Redwood City and Menlo Park stations. A third-party project may have construction crews trimming trees in Redwood City near Main St and Pennsylvania Ave.

 

Mountain View to Santa Clara

Crews will resurface rail between the Mountain View and Santa Clara stations. Caltrain uses several different on-track, self-propelled machines to resurface rail, and neighbors may experience maintenance noise during this time. Crews will work as quietly as possible.

 

Construction crews may be making repairs and replacing parts of a fence near the tracks in Sunnyvale and Santa Clara. Work may also be done near the Mountain View station to repair and replace traffic poles.

Sunnyvale construction crews may be working on Fair Oaks Ave bridge over the Caltrain tracks.

0 0 votes
Article Rating
Subscribe
Notify of
guest

This site uses Akismet to reduce spam. Learn how your comment data is processed.

0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments