Kilroy Oyster Point // Scheduled Power Outages October 1st, 2nd

South San Francisco, CA   September 16, 2019 Submitted by Kilroy Oyster Point

To Members of the Oyster Point Marina Community:

Teichert Construction has scheduled power outages occurring on Tuesday, October 1st and Wednesday, October 2nd. Below you may find the scheduled activities for each day:

October 1st, 7 am – 9 pm
– De-energize (0.5 hrs.)
– Relocate Gear to new pad (3 hrs.)
– Pull Wire for feeder/service (0.5 hrs.)
– Cutover on Piers (10 hrs.)

October 2nd, 10 am – 1 pm

– De-energize (0.5 hrs.)
– Pull feeder/service and make connections (2 hrs.)
– Energize (0.5 hrs.)

We and Teichert Construction welcome any comments you may have regarding this work and thank you for your patience during this time.

Sincerely,
Kilroy Oyster Point Development Team

Oyster Point Hotline
(415) 808-6030
oysterpointhotline@kilroyrealty.com

Teichert Construction
John Bridges
(925) 750-4582
jbridges@teichert.com

0 0 votes
Article Rating
Subscribe
Notify of
guest

This site uses Akismet to reduce spam. Learn how your comment data is processed.

0 Comments
Inline Feedbacks
View all comments